Saturday, November 15, 2014

Barn: progress report...

Barn: progress report...  The siding crew was here again yesterday.  They installed the tarpaper and mesh base for the rock that will be on the lower four feet of our barn's wall.  The roofers were here to repair some underlayment that had blown off, and to install flashing between the second floor walls and first floor roof.  On Monday the siding crew will install the second floor siding, and possibly start on the rock.

I spent a few hours on the tractor, filling the electrical trench in (covering the conduit).  On Monday I'll be getting a load of road base, and I'll be using it to put in the base for the barn's transformer.  If it dries out enough, I'll be trenching for water, gas, and network on Sunday...